Case Study

Building Management Company

Case Study:

Building Management Company

Chiller Replacement


The Issue

The building owners needed to replace an old unreliable York chiller as their tenants, a large insurance company, were experiencing disruptive climate control in their Head Office. The old York chiller had been installed in the building to hide it from view, which meant the job was made particularly difficult as there was no space in the building for good access.


The Solution

We proposed a Tetris 62.8, which had a smaller footprint and 80pa fans. These were removed before the chiller was positioned through the building doors and refitted once in place.


Outcomes

The client had reliable cooling after one of the hottest summers. There is also now more space inside the building for service and maintenance.